Federal Court cancels meeting for proposed scheme of arrangement

Ruling says holding such a meeting will not be useful in the circumstances

Federal Court cancels meeting for proposed scheme of arrangement

Australia’s Federal Court has cancelled a meeting of the plaintiff’s shareholders scheduled to consider and potentially approve a proposed scheme of arrangement between the plaintiff company and its shareholders. 

In Platinum Capital Limited, in the matter of Platinum Capital Limited, [2025] FCA 925, the court made 7 July 2025 orders convening a meeting of the plaintiff’s shareholders at 12:00 p.m. on 12 August 2025, as well as ancillary orders. 

The meeting aimed to consider and, if deemed fit, approve a scheme of arrangement proposed between the plaintiff and its shareholders. 

The plaintiff applied under s 1319 of the Corporations Act 2001 (Cth) to cancel the meeting convened under s 411(1) of the Corporations Act and vacate the orders relevant to holding the meeting. 

The plaintiff alleged there would be no utility in holding the scheme meeting because the required majorities would not likely pass the scheme resolution, given the opposition of the substantial shareholder, L1 Capital. 

The parties to a scheme implementation deed executed a deed terminating this earlier deed on 5 August 2025, as confirmed by an ASX announcement that day. 

Also on 5 August 2025, the plaintiff released an ASX announcement stating that: 

  • The board believed that the scheme would not get the support it needed to meet the 75 percent approval threshold and that withdrawing the scheme would serve the shareholders’ best interests, considering anticipated voter turnout and the notified intention of L1 Capital and its associates to vote against the scheme with their approximate 17 percent holding 
  • The general meeting scheduled for 1:30 p.m. on 12 August 2025 would proceed and address a proposed on-market buy-back 

Meeting cancelled

The order of the Federal Court of Australia

  • cancelled the scheme meeting convened by the plaintiff 
  • vacated orders 4 to 10 of the 7 July 2025 orders
  • vacated a hearing scheduled for 15 August 2025 
  • otherwise dismissed the proceeding 

The court determined that it had power under s 1319 of the Corporations Act to cancel a scheme meeting convened under s 411(1) of the Corporations Act if there was no utility in holding the meeting. 

In this case, the court found it appropriate not to push through with the plaintiff’s scheme meeting, given that: 

  • The meeting would have no utility 
  • The scheme implementation deed had been terminated 
  • The deed’s remaining in force was a condition for the scheme to become effective